TSH Construction Update: Pic of the manhole for sanitary sewer manhole beside the building and beginning to excavate for the parkade. Pit for main elevator. Lots of underground conduit for data and power lines into the mechanical room. Phase 2 floor is poured with many underslab plumbing and electrical conduits poking up. Phase 1 exterior and interior walls are standing. Posted on July 3, 2025July 3, 2025 by utilities@town.trochu.ab.ca
Trochu Transfer Station Notice : All Fridges & Freezers will be inspected before being accepted, If not empty they will be refused ! Posted on July 3, 2025July 3, 2025 by utilities@town.trochu.ab.ca
Trochu ATB Financial’s NHL Stanley Cup Playoffs 50/50 winner Is Isabel Whyte! Isabel chose the Trochu Housing Corporation as her designated charity. Isabel also generously decided to donate her half of the pot back to the organization, resulting in a total donation of $376.00 to the Trochu Housing Corporation. ATB will be hosting a Community BBQ Thursday, June 26, 2025 from 11am – 1pm. Please join ATB for a free lunch and meet the ATB Trochu team. Posted on June 23, 2025June 23, 2025 by utilities@town.trochu.ab.ca
Trochu Senior Housing construction update: Some aerials of the construction site. Large excavating equipment installing manholes for sanitary sewer and storm sewer. Water lines already installed. Grey under slab plumbing being laid. White underfloor electrical conduit to run power lines through. Green poly being laid over gravel base in preparation for cement floors. Smaller excavation equipment digging trenches for plumbing and electrical lines. Including shovels and wheelbarrows. Foundation walls for Phase 5 being built. Coring holes through cement walls for power and sewer lines. Dozens of stacks of prebuilt walls lined up. Posted on June 11, 2025 by utilities@town.trochu.ab.ca
Trochu Seniors Housing Construction Update – Proceeding with footings and foundation of Phase 5. Notice large excavation pit for main elevator. Underfloor plumbing for Phase 1 is underway. Walls are being prebuilt under tent cover to be erected soon. Almost completed all walls for Phase 1 and 2 for 2 floors. Notice pics of stacks of walls. Underground utilities materials have been delivered. Water, sewer, and storm sewer supplies are onsite. Posted on May 30, 2025May 30, 2025 by utilities@town.trochu.ab.ca
Trochu Senior Housing Construction update: Some lumber has been delivered to site. A tent building is being constructed to frame walls within. Walls will then be moved and stood up in final position. Phase 3 and 4 footings are poured. Foundation wall forms are being set for these areas. Continuing to backfill Phase 2. Posted on May 2, 2025May 2, 2025 by utilities@town.trochu.ab.ca
Trochu Seniors Housing Construction update: Lots of metal is embedded in the concrete footings and foundation. 2” Styrofoam insulation is outside the foundation walls to help keep frost out. Phase 1 is mostly backfilled. Started backfilling Phase 2. Footings poured on Phase 3 and framing begun for foundation walls. Started digging trenches for Phase 4. Posted on April 14, 2025April 14, 2025 by utilities@town.trochu.ab.ca
We are backfilling phase 1 foundation walls as well as digging phase 2 footings and pouring phase 3 foundation walls Posted on April 1, 2025April 1, 2025 by utilities@town.trochu.ab.ca
Here’s some aerial pics for your scrutiny. The first 2 Phases are southern end of building. Supportive Living. The building will extend to the north from here with the parkade and Independent Living being the final Phase for construction. Posted on March 26, 2025March 26, 2025 by utilities@town.trochu.ab.ca
Trochu Seniors Housing Construction update: Phase 1 foundation walls are curing with exterior sealant rolled on. Forms are all laid out for Phase 2 footings being poured. Cement trucks dump into hopper of cement pumper unit. Hoses and tarps are still covering Phase 3 to thaw frost. Posted on March 25, 2025March 25, 2025 by utilities@town.trochu.ab.ca