Recently Margie Frere made a donation of $25,000. The funds will go towards The Bistro/Coffee Bar which will be an area in the new Seniors Housing Complex. Margie is a forever resident of Trochu, and she currently resides at St. Mary’s Lodge. She’s looking forward to moving into her new space and no doubt you’ll will see her enjoying a cup of coffee at The Bistro. ☕️🫖 Thank You Margie for giving back to your community. ❤️⭐️ There are several opportunities left to contribute to different areas in the new complex. If you are interested or know someone interested in sponsorship opportunities please reach out. Posted on February 18, 2026 by utilities@town.trochu.ab.ca
TSH Construction Update: Aerial progress pics. Notice walls for hallway in independent living are standing, and beginning work on exterior walls for level 1. Roofing complete for Phase 1,3, and 4. Third floor to begin soon on Phase 5. Most days have around 40 people on site between all the different trades Posted on February 5, 2026 by utilities@town.trochu.ab.ca
THC Construction Update: Couple pics of the front entrance. Covered by orange and white tarp with double elevator shaft nearby. Exterior pics of Phase 1 and 3. 1st floor framing on Phase 5 (lodge, entrance, and area leading to independent living). Concrete floor of independent living. Pic of underground parking. Couple pics of Phase 5 framing. Several pics of Phase 1 and 3, drywall, electrical, plumbing, insulation, HVAC. Pic of Phase 2 framing. Couple pics of Phase 4 (mechanical wing) with mechanical, electrical, and plumbing equipment. Posted on January 29, 2026January 29, 2026 by utilities@town.trochu.ab.ca
Update for Town’s new Northwest Subdivision. Water and sewer lines being installed to service new planned residential lots. Mainlines being installed underneath the new Doctors Way street to service Trochu Seniors Housing. Pic of heavy equipment working and of infrastructure to be buried Posted on December 5, 2025 by utilities@town.trochu.ab.ca
Exterior siding for Phase 1 and 3 are coming along. Pic of AC unit to be roof mounted. Pic of concrete block elevator shaft. 1st floor of Phase 2 framed. Starting on 2nd floor. Concrete block of 2nd elevator shaft in Phase 5 completed. Some framing on Phase 5. Pic of preparation of suspended concrete floor above parkade in Phase 6. Pic of framed walls within Phase 4 (mechanical area). Several pics of various states of interior on both floors within Phase 1 and 3. Electrical, plumbing, drywall, insulation, HVAC, interior framing all continuing to be developed Posted on December 5, 2025December 5, 2025 by utilities@town.trochu.ab.ca
Trochu Housing Corporation Construction update: Progress is being made. Cinder block walls being erected on Phase 4 (Mechanical wing). Cinder block firewall between Phase 3 and Phase 5 main areas. Phase 1 HVAC ducts, plumbing, electrical, and hanging drywall ongoing. Lots of wire, pipe, and ducts will be hidden behind walls and ceilings. Steel beams and posts in Phase 5. Concrete floor poured on Phase 5. Foundation concrete walls poured for parkade of Phase 6. Storm sewer manholes and structural footings are being added to parkade floor. Posted on September 24, 2025 by utilities@town.trochu.ab.ca
Northwest Subdivision Phase 1 construction update: Heavy equipment is on location to begin Town of Trochu new subdivision earthwork. Will be running water, sanitary sewer and storm sewer lines to supply and service Seniors Housing project. Rough grading new streets. Digging storm pond for water collection. Servicing 26 new residential lots. To be completed in 2026. Posted on August 26, 2025August 26, 2025 by utilities@town.trochu.ab.ca
TSH Construction Update: Pouring footings between Phase 5 and Phase 6 (independent living). Exterior and interior of Phase 1. More steel supports and beams in Phase 5. Lot’s of blueprints for construction direction in the contractor’s shack. Posted on August 22, 2025August 22, 2025 by utilities@town.trochu.ab.ca
TSH Construction Update: New concrete floor being power troweled in Phase 4. Pics of electrical conduit running underfloor into Phase 5. Concrete floor finished under Phase 3 with steel beams and supports. Phase 6 parkade is excavated and forms are being laid. Couple pics of foundation wall forms set up waiting for concrete. Phase 1 framing almost complete with roof trusses being set up. Posted on August 14, 2025August 14, 2025 by utilities@town.trochu.ab.ca
TSH Construction Update: Aerial pics. 2nd floor of Phase 1 is almost complete. Green plastic is laid under Phase 3. Almost ready to pour concrete slab. Phase 2 concrete slab is curing. Phase 6 (independent living with underground parkade) is 95% excavated and starting to lay concrete forms for footings. Backfilling Phase 4 after underground services installed. Beginning to dig trenches in Phase 5 for underground services. Posted on August 1, 2025 by utilities@town.trochu.ab.ca