Trochu Senior Housing construction update: Some aerials of the construction site. Large excavating equipment installing manholes for sanitary sewer and storm sewer. Water lines already installed. Grey under slab plumbing being laid. White underfloor electrical conduit to run power lines through. Green poly being laid over gravel base in preparation for cement floors. Smaller excavation equipment digging trenches for plumbing and electrical lines. Including shovels and wheelbarrows. Foundation walls for Phase 5 being built. Coring holes through cement walls for power and sewer lines. Dozens of stacks of prebuilt walls lined up.

Trochu Seniors Housing Construction Update – Proceeding with footings and foundation of Phase 5. Notice large excavation pit for main elevator. Underfloor plumbing for Phase 1 is underway. Walls are being prebuilt under tent cover to be erected soon. Almost completed all walls for Phase 1 and 2 for 2 floors. Notice pics of stacks of walls. Underground utilities materials have been delivered. Water, sewer, and storm sewer supplies are onsite.